NWH 0.26% $3.92 nrw holdings limited

Ann: NRW awarded FMG's Stage 1 Eliwana Rail Project, page-5

ANNOUNCEMENT SPONSORED BY PLUS500
ANNOUNCEMENT SPONSORED BY PLUS500
CFD TRADING PLATFORM
CFD Service. Your Capital is at risk
CFD TRADING PLATFORM CFD Service. Your Capital is at risk
ANNOUNCEMENT SPONSORED BY PLUS500
CFD TRADING PLATFORM CFD Service. Your Capital is at risk
  1. 2,320 Posts.
    lightbulb Created with Sketch. 170
    There is more to come from Eliwana. As ellimb suggests, this Announcement may cover the same work as the 31/12/2018I Announcement,  except the value has increased marginally, and a formal contract has now been executed. The original Announcement stated:

    NRW Preferred Contractor for Fortescue’s Eliwana Rail Project Stage 1

    NRW is pleased to announce it has been selected by Fortescue Metals Group Ltd (Fortescue) (ASX:FMG) as the preferred Contractor to deliver the Stage 1 Earthworks, Roadworks and Drainage Works of Fortescue’s Eliwana Rail Project.

    Fortescue and NRW will move to finalise outstanding matters prior to formal contract execution.

    The project value is circa $57m. NRW will utilise its existing civil construction fleet for the project.


    As I then wrote in respect to the following list:

    Work packages 2, 3, 5 and 20 have either been awarded (e.g., package 3), or they may be potential wins for NWH.
    1. Transformers .. 24/08/18–07/01/19
    2. Bulk Earthworks for Processing Plant and Non-Process Infrastructure
      ..... 23/10/18–01/02/19 Target Award 03/19
    3. Eliwana Bulk Earthworks and Roads .. 21/08/18–31/08/18 Target 3/10/18
    4. Rail Camp 50 and 95 .. 24/08/18–14/09/18
    5. Bridge Contractor .. 24/08/18–17/09/18 Target Award 5/1/19
    6. Bridge Girder Supply .. 24/08/18 – 17/09/18
    7. Supply of Sampling Equipment .. 24/08/18 – 20/09/18
    8. Apron Feeder .. 23/08/18 – 21/09/18
    9. Railway Ballast Supply and Delivery .. 21/08/18 – 10/09/18
    10. Potable water treatment Plant .. 23/08/18 – 12/10/18
    11. Construction Communications .. 18/09/18 – 19/10/18
    12. Rail Communications .. 18/09/18 – 19/10/18
    13. Eliwana Early Mining Fleet Maintenance and NPI .. 28/09/18–26/10/18
    14. Conveyor Drives .. 17/10/18 – 27/10/18
    15. Earthworks Eliwana rail - 20 to 143km .. 18/09/18–31/10/18 Target 4/19
    16. Tramp Metal Magnets .. 26/10/18 – 05/11/18
    17. Low Voltage Switchrooms .. 16/10/18 – 08/11/18
    18. High Voltage Switchrooms .. 16/10/18 – 09/11/18
    19. Grade Control Reverse Circulation Drilling .. 23/10/18 – 20/11/18
    20. Primary Crushing and Ore Processing Facility .. 30/10/18 – 22/11/18
      Target Award 20/3/19
    21. Diesel Power Generation .. 06/11/18 – 23/11/18
    22. Stockyard and Overland Conveyor Construction .. 18/10/18 – 23/11/18
    23. Train Loadout Facility and Train Loadout Conveyor Construction
      .. 18/10/18 – 23/11/18
    24. Low Voltage Variable Speed Drives .. 31/10/18 – 26/11/18
    Last edited by Pioupiou: 15/02/19
 
watchlist Created with Sketch. Add NWH (ASX) to my watchlist
(20min delay)
Last
$3.92
Change
0.010(0.26%)
Mkt cap ! $1.574B
Open High Low Value Volume
$3.97 $3.97 $3.86 $4.473M 1.141M

Buyers (Bids)

No. Vol. Price($)
5 11521 $3.91
 

Sellers (Offers)

Price($) Vol. No.
$3.93 14574 3
View Market Depth
Last trade - 16.10pm 21/11/2024 (20 minute delay) ?
NWH (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.