It’s impossible to put exact dates on when we could expect a JORC. We’re drilling into the unknown. And we’re planning to go deep.
I think when you account for mobilisation, drilling and demobilisation for each hole it’s safe to allow four weeks per hole at 400m. That’s not making any allowance for the extra depth we know we have in the south - and I think JP will want to drill as deep as the geology allows him (I don’t even know the maximum depth capability of this type of rig). On top of that I would make allowances for holes collapsing, hitting rock etc. If we finish drilling in 6 months I’d be happily surprised. More like 7-8 months imo. Then an extra month or so to finish off the assays.
Then - assuming 5 holes gives us enough data - I’d say an extra 2-3 months to produce a maiden JORC.
So anywhere from 9-12 months is my best guess. If we have it before Xmas I’ll be happy.
- Forums
- ASX - By Stock
- GLN
- General Discussion Banter GLN
General Discussion Banter GLN, page-1067
-
- There are more pages in this discussion • 1,173 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Add GLN (ASX) to my watchlist
(20min delay)
|
|||||
Last
12.5¢ |
Change
0.000(0.00%) |
Mkt cap ! $60.50M |
Open | High | Low | Value | Volume |
12.5¢ | 12.8¢ | 12.3¢ | $212.1K | 1.694M |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
6 | 295680 | 12.5¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
13.0¢ | 2021999 | 6 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
1 | 50000 | 0.115 |
7 | 472031 | 0.110 |
11 | 947628 | 0.105 |
25 | 1490999 | 0.100 |
2 | 20000 | 0.099 |
Price($) | Vol. | No. |
---|---|---|
0.125 | 1573785 | 9 |
0.130 | 254710 | 7 |
0.135 | 293280 | 3 |
0.140 | 225541 | 3 |
0.145 | 344396 | 6 |
Last trade - 16.10pm 29/11/2024 (20 minute delay) ? |
GLN (ASX) Chart |