    Cobalt price is indeed climbing after a period of stagnating around the 56K mark.

    What is the timeline for the Cobalt production? we have heard no progress reports (on-track or not) since the purchase and that they are hitting their upgrade milestones.

    The original notice dated 21/2/2017 puts a timeline of 6 months to commence mining - which obviously puts it at 21/08/2017. I assume this is on track?

    "Detailed mine planning and optimisation work underway on the Kipushi Cobalt Tailings Project, with the JV aiming to commence mining activities/tailings retreatment within 6 months"

    The Company has executed the Agreement with Paragon to establish a new joint venture company (JVCo), with the following objectives:
    (a) to commence mining activities at Kipushi within 6 months;
    (b) to immediately commence exploration activities on Kasombo;
    (c) to complete a Feasibility Study on Kasombo within 18 months;
    (d) to commence mining activities at Kasombo within 24 months; and
    (e) to identify and secure other copper, tin, zinc, and cobalt projects in the DRC and Zambia to advance towards commercial production.

    Note: TS never hits promised dates - let us hope this is the exception.
 