Was just looking at a work timeline as per announcements and BOM rainfall data to figure out how much exploration work was done at The Lake before work was ceased because of the unusual rainfall received.
As announced, Air Core Drilling & Sampson EM Work commenced at The Lake on 23-1-17.
Weather was fine for 14 or 15 days before the big rains commenced on 8th Feb for 5 days straight, throught to the 12-1-17 from BOM rainfall data - Over 93mm of rain recorded at Mt Ridley over the 5 days. Mean monthly avg is 26mm
Work recommences again from the 27-2-17 as announced.
With the results we are waiting on, would they have completed the Sampson EM work at The Lake in that 2 week dry period and a good bit of air core drilling for the report we are waiting on?
Hope we get the results of whatever they did manage to complete next week.